The correct option is (a) list
Explanation: However, on a much larger scale, a ‘schedule of rates term contract’, ‘term contract’ or ‘measured term contract’ may be used when the nature of work required is known but it cannot be quantified, or if continuity of programme cannot be determined. In the absence of an estimate, tenderers quote unit rates against a document that is intended to cover all likely activities that might form part of the works.