Correct choice is (a) True
The explanation is: For 1 : 2 : 4 concrete, 1m^3 need Labour constant.
Mixing concrete = 3.00 hour/m^3.
Lifting and carrying concrete = 1.20 hour/m^3.
Compacting concrete = 0.80 hour/m^3.
Levelling surface of concrete = 0.10 hour/m^3.
Total= (3+1.2+0.8+0.1) = 5.