Which of the following is not a method used for preparing approximate estimates?
(a) Cubical contents method
(b) Unit base method
(c) Plinth area method
(d) Cylindrical base method
I have been asked this question by my school principal while I was bunking the class.
The question is from Types of Estimates topic in chapter Rate Analysis, Estimation and Costing of Construction & Building Materials