Which of the following is the correct order of stages of estimation of concrete roads?
(a) Earthwork excavations, cement concrete for the base course (1:4:8) and cement concrete for wearing course (1:2:8)
(b) Earthwork excavations, cement concrete for wearing course (1:4:8) and cement concrete for the base course (1:2:8)
(c) Earthwork excavations, cement concrete for the base course (1:6:9) and cement concrete for wearing course (1:7:9)
(d) Cement concrete for the base course (1:2:3), cement concrete for wearing course (2:7:9) and earthwork excavations
I had been asked this question by my school principal while I was bunking the class.
The question is from Labour and Rate Analysis in section Rate Analysis, Estimation and Costing of Construction & Building Materials