In bar charts, which colour is used to show the actual progress?

(a) Red

(b) Black

(c) Blue

(d) Green

I have been asked this question in an online quiz.

My doubt stems from PERT and CPM topic in chapter Building Plans, PERT and CPM of Construction & Building Materials

1 Answer

+1 vote
by (1.2m points)
selected by
 
Best answer
Right answer is (d) Green

Easiest explanation: In bar charts, different colours are sometimes filled in the bars for showing various control information. For actual progress, green colour is used. For anticipated progress, black colour is used and for progress behind schedule, red colour is used.