Which technique is applicable when other projects in the same analogy application domain have been completed?
(a) Algorithmic cost modelling
(b) Expert judgement
(c) Estimation by analogy
(d) Parkinson’s Law
I got this question in an interview.
The question is from Size and Cost Estimation of Software topic in section Software Management of Software Engineering